In OJSC “FGC UES” the work of the Media Holding “RusCable” was highly appreciated
29 дек. 2015, 18:02
2542
Within the bounds of the exhibition “Electric grids Russia-2015”, on December 2nd the round-table conference “Import substitution: boarders of power safety”, organized by OJSC “FGC UES”, took place.
The general information partner and co-organizer of the event was the media holding “RusCable” and the RusCable.ru portal.
“High professionalism of...
Tests with operating voltage STATKOM has started as part of a complex transformative innovation in the Baikal region
08 апр. 2014, 19:29
2624
At the 220 kV Mogocha substation, the branch of JSC " FGC UES " (included in the group of companies of " Rossetti ") - Trunk Power Grids ( MEA ) of Siberia - in the period from December 2013 to March 2014 , the installation and testing of equipment STATCOM -1 was performed: Cooling System of voltage converter , filter- , battery static capacitors ,...
JSC «UES FGC SEC» took part in the Russian Internet Week - RIW-2013
28 окт. 2013, 10:09
5546
Since 17 till 19 October the 6 annual Russian Internet Week took place in Moscow Expocentre (Russian Internet Week, RIW–2013).
Russian Internet Week 2013 was a multi-threaded three-day conference, with the program which included more than 100 conference events, large-scale exhibition "INTERNET 2013", lots of extracurricular activities, presentati...
Power cables «ELECTROCABLE» have been vetted by JSC «FGC UES» (JSC «Rossetti»)
18 окт. 2013, 10:51
2955
The plant "Electrocable" once again confirmed the high quality of its products.
JSC "FGC UES" (JSC "Rossetti") has certified the following products, produced by JSC "CZE":
- Power cables , flame retardant , with low smoke and gas emission with 0.66 and 1 kV, brands VVGng (A )-LS, VVGEng (A )-LS, AVVGng (A )-LS, AVVGEng (A )-LS , VBShvng (A )-L...
Компания:
Tests of HTS DC cable line were taken by JSC «FGC UES SEC”
03 сент. 2013, 13:15
2451
The creation of a superconducting cable line DC for the St. Petersburg power supply with the capacity of 50 MW is held by LLC "UES FGC" . This August tests two of 30 -foot lengths of bipolar HTS DC cable assembly with two end and a coupling on the transmission power of 50 MW were carried out.
The cable was developed by JSC " FGC UES SEC " and manuf...
In the flooded regions of the Far East a unique repair work is being held
27 авг. 2013, 15:55
2078
The affiliate of JSC "FGC UES" (a member of the group of companies "Rossetti") - MES East - repaired one-base support of 220 kV transmission line Skovorodino for the first time in the Far East- Tynda without stress relief and limitations of power supply. The works were carried on in frames of preparation for the autumn-winter period in a complex fl...
Federal Railways and FGC discuss electrification of railway infrastructure on the Taman Peninsula - Yakunin
20 авг. 2013, 17:44
1813
The Federal railways and FGC discuss the issues of railway electrification on Taman Peninsula, the President of Railway Monopoly informed.
“The most complicated subjects is no doubt railway infrastructure electrification on Taman Peninsula, we are leading negotiations with our net company FGC. They seem to prove the availability of plans to create...
JSCo «UES FGC» has received long-term funds from Vnesheconombank in the amount of 26 billion rubles
14 авг. 2013, 17:25
1889
JSCo “UES FGC” (a member of company groups JSCo “Rossetti”) attracted a new tranche of long-term finances through the issuance of infrastructure bonds of series 26 and 27 for a total of 26 billion rubles. The term of repayment for bonds is 35 years. The offer is in 34 years.
The bond issue is intended to fund projects under the investment program